Jun 19, 2024
Contractor Penalized for Delays at North Pattaya Intersection
Deputy Mayor Manot Nongyai has imposed daily fines of 114,125 baht on the responsible contractor for delays in the North Pattaya intersection construction project. The project involves resurfacing key intersections across Pattaya, with penalties in place until completion. Excavations and closures are scheduled from June 17 to 25, with a focus on expediting work by month-end. Manot hinted at potential blacklisting for future unreliable contractors and emphasized the strict enforcement of contractual terms. In Sri Racha, residents and business owners are demanding immediate action to resolve a construction debacle at the Bang Phra-Klong Sukreeb junction.